Dig Activity in 2006

Home Up Dig Activity in 2005 Dig Activity in 2006 Dig Activity in 2007 Dig Inactivity in 2008 Dig Activity in 2009



The Courtesan, Agen Allwedd

Highlights of the Year

During this year we:

  • extended the main route by several feet- back under an arched roof.

  • uncovered another passage to the left near the dig face where the roof is going up again.  The side passage is not quite full to the roof.

  • found some 'black space' on the right hand side of the cross-rift which we haven't pushed yet.

The Dig Log

Weekend 28th/29th January  The water was at 'normal level' with only a foot of so of water in the extension passage.  Pumping took less than an hour.  It was found that several tons of infill had fallen out of the roof of the cross rift exposing the ceiling and about 6 feet of passage to the right - not in the direction we want to go but another 6 feet for the survey nevertheless.  There was evidence of recent flooding right up to the cave roof.
All of Saturday (which was bitterly cold with a biting wind) was spent removing the infill from the collapse (not a new experience for the team!) - 75 buckets in total. By dusk it was too cold to continue.
Most of Sunday was also spent removing the infill from the collapse but in the late afternoon we did manage to add a couple of feet to the system, digging under the arched roof we had spotted last July.
At floor level the infill is like shale sand and is only loosely packed - the next weekend which has been provisionally set for  25th/26th March promises to be very interesting.

The Dig Team: MCa (Sun only), KEd, BMa (Only for a couple of hours each afternoon), MNo, GSm, JSm, ASt + Gary from SWCC (Sun only)


Saturday 25th March  The water slightly higher than 'normal level'.  Pumping took nearly all day.  When we got to the bottom of the extension passage it was noted that more infill had fallen out of the roof and had washed down to the dig face.  Also by this time the rain which had started when we started pumping had set in for the day and was falling heavily.  Water was pouring in from both the left and right-hand sides of the cross rift.  In fact the water on the left was falling as a waterfall!  At this stage we abandoned operations for the day.
While we were waiting for the water to be pumped out we dug up in the aven on the left-hand side - following the roof and one wall.  This dig had been started several years ago.
It rained heavily overnight on the Saturday night.
We returned on Sunday knowing that there would be too much water in the system to dig at the face, but we thought that we would be able to get the sand from the dig in the aven out to surface, but the water was well up the main railway track!  So we packed up.

The Dig Team: KEd, BMa, GSm, JSm, ASt & CWe


Weekend 24th/25th June  A very successful weekend.  After a dry week there was no significant water at the dig face, so with no pumping required we were able to start digging straight away.  On Saturday we were able to remove the infill which had fallen out of the cross rift and make a little forward progress under the arched roof.  We had to replace the drag tray which which had lost all of its rigidity, but the replacement (an old washing up bowl) completely disintegrated after only about 10 uses.  Nevertheless we did shift 140 buckets.
On Sunday we fabricated a new drag tray and in spite of having to re-tyre two of the truck wheels we added another few feet to the system and shifted another 110 buckets.  In the afternoon we managed to drop a boulder out of the roof which revealed some "black space", but after much excitement we found after a few feet the infill was back up to the roof.

The Dig Team: PAn (Sun only), MBo, MCa, KEd, BMa, MNo (Sun only) DRo, GSm, JSm & ASt


Weekend 12/13th August  We now have 150, 13" x 30" sand bags - each one holds more than a bucket full.  On Saturday we filled 100 bags (approx. 120 buckets) and stacked them at the bottom of the main railway track.  With only 4 people we had to initially stack the bags in the cross-rift and then move positions to get them to the bottom of the entrance passage.
On Sunday we pulled 80 bags out to surface before the front wheels of the main dig truck were worn so badly that they splayed out and came off the railway track.  We took both trucks back to the workshop and swapped two wheels between the trucks.  We were then able to drag out the remaining 20 bags.  After this we filled another 50 bags and stacked them in the cross-rift.
Over the course of the weekend we added approx. 10 feet to the system.  Near the dig face we have lost the roof again, but we think that at the dig face we may have got the roof back.  Also on the left there may be a side passage.


Keith in the cross rift stacked with sand bags.  This view is looking back towards the entrance.

Keith under the wedged boulder in the roof. This view is looking back towards the entrance.

The Dig Team:  JDu (Sat and Sun morning only), KEd, CJe (Sun only), BMa and DRo


Weekend 30th September/1st October  After a very wet week we thought that digging would be impossible but when we looked down the cave on the Saturday morning the water level was below the cross-rift.  Setting up and pumping took over 4 hours, but afterwards we were able to dig for about 3 hours.  While the water was being pumped out Keith and Brendan removed some of the in-fill from the right-hand side of the cross-rift.  Ahead at the top of the passage we can see some significant black space!
By the end of the day we had moved all of the newly filled bags and all of those from the left-hand side of the cross-rift (left behind from our last visit) to the bottom of the main railway track.  Water running in was a constant problem and all of the digging was done kneeing in water.  Back at the caving club it took well over half an hour and most of the members of the dig team to remove Mr Smith Senior's wellies!
At the dig face nearly all of the in-fill from the 'lost' roof of the passage had slumped in revealing back space in the ceiling.  After some digging we were able to climb up into this.  The passage here is around ten feet high.  Ahead appears to be the continuation of the chocked narrow rift, above is a 4 inch square hole in the roof which is another inlet, but to the left is (as we suspected from last time) another passage and the in-fill does not go quite up to roof level - more black space!  We can see about six feet along this passage before it appears to turn right again.  This is a very interesting area.
Saturday evening and  night were moist to say the least so on Sunday morning all we were able to do was to pull all of the bags out from the bottom of the main railway track.  Mr Smith Senior insisted that he would have to work on the surface only as he didn't want to have the same problem removing his wellies.  After 15 minutes it started to rain heavily so he spent the rest of the day in the library reading and drinking tea.  In the afternoon a couple of us went down to look at the water level and it was back to the height that we had found it at the previous morning.  It seems that the water quickly drains to this level which is very good news.
Before was can operate the dig again we will have to do much needed remedial work on the dig truck and track as well as permanently fixing the dig hoses and rewiring the pump cables.


The black space at roof level in the right-hand side of the cross-rift

The Dig Team:  MCa, KEd, BMa (Sat only), DRo, GSm (Sat & first 15mins of Sun only), JSm & ASt


Sunday 15th October  We had a look in the dig and the water level was up to the timbers in the extension passage with only about a foot of air space to duck through to get into the cross-rift.  The arch leading to the dig face was under water.  The water is not draining as quickly as we had hoped!  Brendan and Keith braved the water to investigate the cross-rift.

Present:  KEd, BMa, DRo and CWe



Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving ClubTop

TO CONTACT US:

PHONE: Keith Edwards on 0121 525 1230 or 07939 042467
or E-MAIL: I've removed the mail to: link to reduce the amount of junk mail I get.  Sorry but now you will need to type my email address into your email client.

Website designed, created and maintained by Keith Edwards.
Copyright Dudley Caving Club 1997 - 2012