Dig Activity in 2005

Home Up Dig Activity in 2005 Dig Activity in 2006 Dig Activity in 2007 Dig Inactivity in 2008 Dig Activity in 2009



The Courtesan, Agen Allwedd

Highlights of the Year

During this year we:

  • cross-rift in extension passage discovered

  • air space found at roof level behind the hanging boulder

  • pumps and generator purchased

The Dig Log

Weekend 28th/30th January  Keith, Brendan, Graham, John and Keith travelled down on the Friday evening.  The water level at the lowest point was just a little over welly height so it was decided to pump it out.  Once the pump had been started this took only about 5 minutes.
Adrian joined the team on Saturday and with Brendan acting as Duty Officer at the club, five of us dug out another 5 feet of passage, removing 105 buckets of infill.
On Sunday the team was strengthened by the addition of Pete, Mick Bowdler, Mike Cavanagh, Jim and Mike Noble.  Approximately 120 buckets of infill was removed.
The passage discovered last August (Extension Passage) is now a little over 20 feet long with solid roof and walls.  It is trending downwards at on angle of approximately 5 degrees and has been dug out to a depth of about 3 feet 6 inches.

The dig team

Pete removing a boulder
 

The new passage - Pete in the foreground and Jim behind

Mike Noble at the dig face

The Dig Team: PAn (Sun only), MBo (Sun only), MCa (Sun only), JDu (Sun only), KEd, BMa, MNo (Sun only), GSm, JSm, ASt & CWe


Weekend 7th/8th May  Another very successful digging weekend.  On Saturday morning we constructed a single-bucket railway over the pool and in the afternoon we removed 75 buckets of spoil.
On the Sunday we removed another 112 buckets of infill.
We appear to have discovered a cross-rift with the passage we have been following, continuing ahead.  Another weekend should confirm this.  During the weekend we added 6 feet to the length of the cave.

The Dig Team: MCa (Sun only), KEd, BMa, MNo, GSm, JSm & ASt


Keith Edwards in the newly discovered cross-rift.


Weekend 11th/12th June  Yet another highly successful weekend's digging by a very small, but highly dedicated team.
After a sunny week we all expected the dig to be dry, but the Extension Passage had a significant amount of water at its lowest point. We managed to bail this back into the main pool and then went to examine the dig face.  There was foam high in the roof of the cross rift indicating that the Extension Passage had recently flooded to the roof.  The water had washed some of the infill out of the passage straight ahead and had exposed a large pointed boulder hanging down from the roof.
Brendan used his electronic draught detecting meter and found a small but significant draught to the left hand side of this boulder.
During the Saturday Adrian continued to dig ahead and managed to get underneath and past the hanging boulder - 60 buckets of infill were removed on the day.  On the far side of the boulder the passage roof effectively disappeared with only sand above the digger.
On the Sunday Keith investigated the roof behind the hanging boulder with the aid of a 4' length of angle iron.  After about half a dozen prods the bar went through to reveal black space.  After about half an hour the hole in the roof was large enough to climb up into.  We are in a narrow rift about 7' 6" high (from the existing floor) with about 3" of air space in both directions.  The passage back to the cross-rift has been dug out to body-size and will connect to the top of this rift.  A small air space can be seen to both left and right along the cross-rift.  The left hand passage (looking into the cave) seems to be an inlet.
Ahead the passage continues with air space at roof level.  Approximately another 5' of this passage has been dug out.  It is a narrow rift - about a foot or so wide and so although air space exists at roof level the passage will have to be dug out to the existing floor level where hopefully it will continue to be wide enough to get through.  Another 36 buckets of infill were removed to surface on the Sunday.


The newly discovered passage looking up-dip, back towards the entrance

 


The newly discovered passage looking down-dip, the way on

The Dig Team: MCa (Sun only), KEd, BMa, MNo & ASt


Weekend 9th/10th July  A large dig team and probably a record for the amount of infill removed - 140 buckets on the Saturday and 120 buckets on the Sunday, but nevertheless a little disappointing.
There was a lot of water in the extension passage and so the first couple of hours on the Saturday were taken up in baling water from here to the main pool and from the main pool to the surface.
When digging commenced it became apparent almost immediately that the rift ahead was joined in the middle.  Above (where the air space is) the passage is too small to follow, below we could see an arched roof.  Unfortunately by the close of play on Saturday is was impossible to remove any more infill ahead as most of the way on was below water.
On Sunday John and Adrian lowered the floor by the dig face and ramped it back along the passage.  Now the water drains to the bottom of the passage and so should be easier to bale out next time.  Before we can go digging again we will need to source a pump.
During the weekend approximately 2 feet was added to the length of the system and about 6 feet to the depth.

The Dig Team: PAn, MBa, DBo (Sun only), KEd, BMa, MNo, JSm, ASt & CWe


Weekend 17th/18th September  Brendan and Keith inspected the dig 3 times during the weekend.  The water was 4' 6" high at the dig face and only drained by about 1.5" during the weekend.  It was estimated that approximately 1000 gallons of water will need to be shifted before digging can again commence.


Thursday 22nd September  Three 550W pumps have now been purchased by the club.  Once we have a generator digging activities will re-commence.


Weekend 29th/30th October  We started pumping operations at 12:45 and the pumping went very well indeed. Everything performed as we had predicted/hoped for and we were shifting the water at over 6 gallons per minute.  Under ‘normal’ circumstances this would have completely emptied the system in a little over 2 hours. Unfortunately South Wales had had (even by its own standards) an excess of liquid sunshine during the preceding 7 days and the water level in the dig was high, in fact very high, in fact there was about 4 times the normal amount of water in the dig, in fact it was completely sumped. So pumping on the Saturday took 8 hours! Never the less we were all set to dig on the Sunday when we retired for the night.
Then during the night it rained, it poured, it was torrential, a deluge, a cloud burst and when we got up in the morning it was still absolutely p'ing down. All of the tracks were rivers, water was pouring out of the party quarry and down the hillside, and all of these water courses were converging at our dig! Now we had left the pumps and the wiring in the dig and so Keith got changed and legged it to the dig see if it was still possible to retrieve these items. It was, just! The archway had about a foot of airspace left before it sumped so he managed to duck through and get the tackle. While he was doing this the water level rose by about 4 inches.
Needless to say we abandoned operations.
When we left Penwyllt the river was a brown ragging torrent and water was resurging in the middle of the field next to it, bubbling up out of the ground.



Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving Club   Dudley Caving ClubTop

TO CONTACT US:

PHONE: Keith Edwards on 0121 525 1230 or 07939 042467
or E-MAIL: I've removed the mail to: link to reduce the amount of junk mail I get.  Sorry but now you will need to type my email address into your email client.

Website designed, created and maintained by Keith Edwards.
Copyright Dudley Caving Club 1997 - 2012